The Wave Stage 2

Project Brief

Client: Laing O’Rourke
Project Value: $6BN
Engagement Period: Dec 2025 – Mar 2026
The Wave Stage 2 forms part of the Queensland Governments broader Sunshine Coast public transport program. The Wave Stage 2 is approximately 7km of dual-track rail extension which includes Aroona and Birtinya stations, Birtinya stabling facilities, a tunnel through Little Mountain, elevated rail structures and road interfaces.
Download Project Sheet

Involvement

Croí personnel were involved in:

  • Utility design and management support during the ECI phase.
  • Development and coordination of the project wide utility relocation strategy
  • Review and refinement of reference utility design and conflict register
  • Development of tender utility treatments, methodologies, quantities, packaging and cost estimates.
  • Development of utility investigation works package in accordance with AS5488.
  • Development of utility construction staging
  • Integration of utility requirements into the overall project programme and construction planning.

Key Achievements

  • Identified and rationalised utility conflicts across the project to establish clear treatment strategies
  • Developed alternative treatments that reduced unnecessary relocations and refined the reference design.
  • Identified opportunities to retain major infrastructure in situ where design changes are made.
  • Developed a coordinated approach to utility investigations, avoiding duplication across adjacent assets and road interfaces.
  • Established utility construction packages aligned with project locations, authorities and broader project construction sequencing.
  • Developed utility construction programs and resource requirements to support tender pricing.
  • Identified critical utility risks and provided advise to manage those risks.

Key Interfaces

  • Queensland Department of Transport and Main Roads (TMR)
  • Unity Water
  • Energex/Energy QLD
  • Telecommunication Carriers (Various)
  • Project design teams
  • Sunshine Coast City Council

Key Benefits

  • Improved confidence in the utility scope, cost and program for tender submission.
  • Clear separation of contestable and non-contestable utility responsibilities.
  • Improved visibility of Utility Authorities interfaces and long-lead activities.
  • Utility Requirements incorporated into broader construction methodology and staging.